14 Wing Greenwood
1. Refuelling Tender Garage
The new facility will include a fire suppression and spill containment system, fume extraction systems, and carbon dioxide detection and warning sensors for maintenance areas.
Value: Approx. $18.9 million (Overall project cost, including taxes)
More information:
•
Fact Sheet - Refuelling Tender Garage
2. Health Services Centre
The new facility will provide direct, comprehensive medical, mental and dental care to the Wing population.
Value: Approx. $26.8 million (Overall project cost, including taxes)
More information:
•
Fact Sheet - Health Services Centre
Completed CFDS Infrastructure Projects
1. Aircraft Mobile Support Equipment (AMSE) Storage Facility
The new facility houses aircraft mobile support equipment so as not to interfere with other detection systems for the CP-140/A Aurora and Arcturus aircraft.
Value: Approx. $2 million (Overall project cost, including taxes)
More information:
•
Fact Sheet - Aircraft Mobile Support Equipment (AMSE) Storage Facility
2. Fire Hall
A new modular fire hall was constructed, located adjacent to the airfield to minimize response time, address training needs, and eliminate current building deficiencies.
Value: Approx. $13 million (Overall project cost, including taxes)
More information:
•
Fact Sheet - Fire Hall
3. Recapitalization of Hangar 14
This project includes structural, mechanical and electrical modifications to Hangar 14 to accommodate two CC-130 Hercules aircraft.
Value: Approx. $3.9 million (Overall project cost, including taxes)
More information:
•
Fact Sheet - Recapitalization of Hangar 14
4. Intermediate Distribution Framework Facility
The Intermediate Distribution Framework facility accommodates all telephone, data copper and fiber connections serving the 14 Wing Greenwood Operations Site. This facility directly supports the flight line recapitalization that will be occurring over the next few years.
Value: Approx. $2 million (Overall project cost, including taxes)
More information:
•
Fact Sheet - Intermediate Distribution Framework Facility