Infrastructure & Environment
Current Infrastructure Projects
Air Force Bases
Navy Bases
Army Bases

19 Wing Comox


4 Wing Cold Lake


17 Wing Winnipeg


16 Wing Borden


8 Wing Trenton


3 Wing Bagotville


14 Wing Greenwood


12 Wing Shearwater


9 Wing Gander


CFB Edmonton


CFB Wainwright


CFB Shilo


CFB Petawawa


CFB Kingston


CFB Montreal


CFB Valcartier


CFB Gagetown
4 Wing Cold Lake
1. Underground Utilities and Roads Upgrade
This project will upgrade all private married quarters residential underground utilities and roads at 4 Wing Cold Lake
Value: Approx. $105.3 million (Overall project cost, including taxes)
More information:
•
Fact Sheet - Underground Utilities and Roads Upgrade
2. Renovation of Building 171
This project involves the construction of a 540 m² second-floor onto building 171, to house all offices of Wing Supply Headquarters. By co-locating these offices in one building, this facility will allow for improvements to supply-related issues. This project also includes a number of renovations and upgrades on the first floor of Building 171 to the current clothing stores section, ductwork and air handling units, the electrical distribution system, telecommunications infrastructure, fire suppression systems, flooring, and flooring. Also included is the construction of a combined conference and training room in building 171. These renovations will increase the Wing’s capacity for administration and training purposes.
Value: Approx. $3.6 million (Overall project cost, including taxes)
More information:
•
News Release - Government Of Canada Modernizes Defence Infrastructure At 4 Wing Cold Lake
•
Backgrounder - Defence Infrastructure Project At 4 Wing Cold Lake
Completed CFDS Infrastructure Projects
1. Petroleum, Oil and Lubricants dispensing system Upgrade
This construction replaced the existing petroleum, oil and lubricants dispensing system, and upgrade the aviation refuelling facility to meet the required environmental standards.
Value: Approx. $8.1 million (Overall project cost, including taxes)
More information:
•
Fact Sheet - Petroleum, Oil and Lubricants dispensing system Upgrade
2. Upgrade Underground Utilities and Roads
The utilities and roads were upgraded to meet the current needs of the Wing, and ensure their longevity. Phase 1 focused primarily on the systems located at the main entry to the Wing.
Value: Approx. $23 Million (Overall project cost, including taxes)
More information:
•
Fact Sheet - Upgrade Underground Utilities and Roads
3. Relocate Aviation Fuel Tank
This project relocated an existing aviation fuel tank from 4 Wing ‘tactical’ tank farm to 4 Wing Base Side tank farm.
Value: Approx. $4.9 Million (Overall project cost, including taxes)
More information:
•
Fact Sheet - Relocate Aviation Fuel Tank